/>
HZS GLOBAL
Home Products About Blog Contact

How Much Power Does a Concrete Batching Plant Need in Africa?

Published: October 2026 | 8 min read | Technical Guide
Concrete batching plant power supply and generator

When a customer in Ghana, Ethiopia or Tanzania opens a batching plant quotation, the electrical drawing is usually not their first worry. Their first question is simpler: will this thing actually run on our power?

It is the right question, and it is the one that most often gets answered too late — after the container has arrived. A batching plant is a cluster of large motors, and how those motors start has more effect on your site than the plant's rated output. This guide covers the numbers you need before you place an order, not after.

Installed power by model

These are the installed (connected) power figures for the standard HZS range. Note the difference between installed power — what you must be able to supply — and average running draw, which is normally lower because the mixer does not run at full load all cycle.

ModelOutput (theoretical)MixerInstalled powerFrom price
HZS6060 m³/hJS1000 (37 kW)110 kW$48,000
HZS9090 m³/hJS1500 (45 kW)150 kW$65,000
HZS120120 m³/hJS2000 (55 kW)190 kW$85,000
HZS180180 m³/hJS3000approx. 260 kW$120,000
HZS240240 m³/hJS4000 (2 x 45 kW)400 kWon request

Voltage and frequency: say it before you sign

Chinese standard is 380 V / 50 Hz. That suits most of Africa, but not all of it:

  • 380 V / 50 Hz — standard build, works across most of East and West Africa, the Gulf, and Central Asia.
  • 415 V / 50 Hz — common on grids in parts of southern and eastern Africa. Motors tolerate the difference in practice, but control transformers, contactors and protection settings should be specified for 415 V.
  • 440 V / 60 Hz — a genuine problem, not a rounding error. At 60 Hz a 50 Hz motor spins 20% faster and draws more current. This needs 60 Hz-rated motors, not a transformer.

Send your actual site voltage and frequency with the enquiry. It is a line on a form at that stage and an expensive retrofit later.

The starting current is what breaks sites

A 55 kW mixer motor started direct-on-line can pull five to seven times its rated current for a second or two. On a weak rural feeder that is enough to trip the breaker, brown out the neighbourhood, or stall every other motor on site. Three ways to deal with it:

  • Star-delta starting — cheapest, cuts starting current to roughly a third. The standard build for most HZS plants.
  • Soft starter — smoother, adjustable ramp, still commonly specified where the grid is poor.
  • Variable frequency drive — best control and useful for tuning cycle times, but adds cost and a maintenance item that many remote sites cannot service.

Whichever you choose, tell us at order stage. Retrofitting a starter into a control panel on site is not a small job.

Sizing a generator

A genset must cover starting current, not just running load. The usual working rule is 1.3 to 1.5 times installed power with star-delta or soft start, and more with direct-on-line starting. Undersizing the genset is by far the most common mistake we see — the plant runs, but the generator stalls at the moment the mixer starts.

PlantInstalled powerPractical genset size
HZS60110 kW150–200 kVA
HZS90150 kW200–250 kVA
HZS120190 kW250–315 kVA
HZS180approx. 260 kW350–400 kVA
HZS240400 kW500–600 kVA

Round up, not down. A genset running at 70–80% load is efficient and long-lived; one running at 100% is neither.

What fuel actually costs per cubic metre

This is the number that decides whether diesel production is viable. A worked example, with the assumptions stated so you can substitute your own:

  • HZS60 at 110 kW installed, running at roughly 70% average load = about 77 kW.
  • Diesel gensets consume roughly 0.21–0.25 litres per kWh delivered, at sensible load.
  • That is about 16–19 litres per hour.
  • At 60 m³/h theoretical output — realistically 45–50 m³/h in service — that is roughly 0.3–0.4 litres of diesel per cubic metre of concrete.

At a diesel price of $1.10–1.40 per litre, fuel alone is around $0.35–0.55 per m³. Compare that with grid power in most of these markets and the conclusion is usually the same: use the grid whenever it is up, and keep the genset for outages. Your own figures will differ with load factor, cycle times and diesel price — the arithmetic above is a method, not a quotation.

Three configurations that work in practice

1. Grid only

Viable where supply is genuinely stable and the feeder can carry the starting current. Cheapest to run. Specify star-delta or a soft starter, and check with the utility what the feeder can deliver before you commit.

2. Grid plus backup genset

The most common arrangement in Africa, and usually the most economical overall. Add an automatic transfer switch so the plant does not sit idle waiting for someone to start the generator. Size the genset to carry the full plant — partial backup that cannot start the mixer is not backup.

3. Genset only

Common on remote project sites with no reliable feeder. Perfectly workable, but budget the fuel per cubic metre honestly into your tender price. Many projects lose money here because the bid assumed grid power that never arrived.

What to put in the purchase order

  • Site voltage and frequency, measured at the plant location — not the city nominal.
  • Starting method required (star-delta, soft starter, VFD).
  • Control voltage — 24 V DC and 220 V AC are both available, and it matters for what your electrician can service.
  • Cable runs from the transformer or genset to the control room, so cable sizing is not left to the site.
  • Earthing arrangement, and whether an earth leakage device is required locally.

Frequently asked questions

Can a 380 V plant run on a 415 V supply?

In practice the motors tolerate it, but control transformers, contactors and protection settings should be specified for the actual site voltage. Declare 415 V at order stage rather than discovering it during commissioning.

How big a generator do I need for an HZS60?

Roughly 150–200 kVA with star-delta or soft starting. The figure is driven by starting current, not by the 110 kW running load.

Can I run the plant on a generator all day?

Yes, and many sites do. Budget roughly 0.3–0.4 litres of diesel per cubic metre at HZS60 scale, and size the genset at 70–80% load so it is not running flat out.

What if our power is 60 Hz?

The plant needs 60 Hz-rated motors. A transformer does not fix frequency. This has to be declared before production, not after delivery.

Does a soft starter increase the price much?

It is a modest addition against the total plant price, and it is far cheaper than upgrading a weak feeder or discovering during commissioning that the mixer trips the site breaker every cycle.

Tell Us Your Site Power

Send site voltage, frequency and whether you have a grid connection, and we will come back with the right configuration and starter type.
HZS60 — 60 m³/h, 110 kW, from $48,000
HZS90 — 90 m³/h, 150 kW, from $65,000
HZS120 — 120 m³/h, 190 kW, from $85,000
Request a factory quotation — reply within 24 hours

Need Help Choosing the Right Equipment?

Contact our team for expert advice and a competitive quote.

Get in Touch

Related Products — Concrete Batching Plants

HZS60 — 60 m³/h, JS1000 mixer, from $48,000
HZS90 — 90 m³/h, JS1500 mixer, from $65,000
HZS120 — 120 m³/h, JS2000 mixer, from $85,000
HZS180 — 180 m³/h, JS3000 mixer, from $120,000
Request a factory quotation — reply within 24 hours

© 2026 HZS Global | Email Us | WhatsApp: +86 187 6888 8850

HZS Global

We reply within 1 hour

Wave Hello! Welcome to HZS Global.

I'm here to help with your concrete batching plant needs.

Just now
Start Chat

Related Articles

Concrete Batching Plant Price in 2026: Complete Cost Breakdown HZS60 vs HZS90: Which Is Right for Your Project? Africa Concrete Plant Market 2026